Deck framing: steel, timber or aluminium?
Which frame suits your deck?
Your deck, framed three ways
Put in the deck’s size and height, what it stands on and anything about the site. The designer’s engine frames it in treated pine, steel and aluminium, and the rules below pick where to start.
For this deck, start with treated pine MGP10. Spantec Boxspan steel is the second choice.
At 600 mm the pine frame has 247 mm of air under it, under WoodSolutions’ 400 mm line, so the designer makes the low parts H4 (a Class 1 hardwood is the other answer). With air moving under it, that is still the ordinary backyard frame. (WoodSolutions use classes) It’s the cheapest frame here, and the easiest to cut and change on site. Steel costs more, but it arrives straight and won’t warp or rot. (Spantec deck page)
| Measure | Treated pine MGP10 | Spantec Boxspan steel | Clickdeck aluminium |
|---|---|---|---|
| Frames it? | Yes: the pick | Yes | Yes |
| Joists | 13 × 140 × 45 MGP10 H3 | 13 × Boxspan B250-20 (250 × 50) | 13 × Clickdeck 150 Multibeam (150 × 50) |
| Bearers | 3 × 2 / 190 × 45 MGP10 H4 | 2 × Boxspan B150-16 (150 × 50) | 3 × Clickdeck 200 Multibeam (200 × 50) |
| Posts or pedestals | 10 posts (90 × 90 H4 post) | 8 posts (Galvanised SHS post 90 × 90 × 2.0 (Ezipier)) | 12 posts (Clickdeck 100 × 100 post) |
| Joist centres | 396 mm | 396 mm | 396 mm |
| Lowest finished height it frames | 253 mm | 223 mm | 79 mm |
| Clearance under the frame | 247 mmlow parts made H4 | 177 mm | 227 mm |
| Frame depth (joist + bearer) | 330 mm | 400 mm | 350 mm |
| Typical frame cost | $2,200–$3,000 | $4,600–$6,000 | $7,400–$8,000 |
Worked by the designer’s engine with its generic Composite 137 × 23 board, joists at 400 mm centres or closer. Concept figures for planning and pricing, not a sign-off.
Want the whole plan?Draw the deck in the free deck designer for its framing plan, materials list and cut list, in any of these frames.
Open the deck designerSteel, timber and aluminium compared
4 frames the designer builds with
Side by side: what each frame is made of, the sizes and lengths it comes in, what it stands on, how low it goes, and what to watch.
| Frame | Treated pine MGP10 | Spantec Boxspan steel | InfraBuild DuraGal steel | Clickdeck aluminium |
|---|---|---|---|---|
| Material | Treated pine, MGP10, H3 or H4; posts F7 H4 | Steel, G550 Z450; posts galvanised SHS | Steel, C450L0 ZB 135/135 | Aluminium, alloy not published |
| Joist sizes (mm) | 90 × 45, 140 × 45, 190 × 45 | B100-12, B100-16, B150-16, B150-20, B150-24, B200-16, B200-20, B250-20 | RHS 75 × 50 × 1.6, RHS 75 × 50 × 2.0, RHS 100 × 50 × 1.6, RHS 100 × 50 × 2.0, RHS 150 × 50 × 2.0 | 28 × 50, 55 × 55, 110 × 50, 150 × 50, 200 × 50 |
| Bearer sizes (mm) | 2 / 140 × 45, 2 / 190 × 45 | B100-12, B100-16, B150-16, B150-20, B150-24, B200-16, B200-20, B250-20 | RHS 150 × 50 × 2.0, RHS 150 × 50 × 3.0 | 28 × 50, 55 × 55, 110 × 50, 150 × 50, 200 × 50 |
| Posts or pedestals | On posts, or pedestals under the bearers. Posts: 90 × 90. Pedestals in the designer: Buzon PB, Paveezzi Rhino SL, Ezy Decking, Sun Decking. | On posts, or pedestals under the bearers. Posts: Galvanised SHS post 90 × 90 × 2.0 (Ezipier). Pedestals in the designer: Buzon PB. | On posts. Posts: SHS 90 × 90 × 2.0. | On posts, or pedestals under the bearers, or joists straight on pedestals. Posts: 55 × 55, 100 × 100. Pedestals in the designer: Clickdeck Pedestal Pro (10–440 mm). |
| Lengths | 2.4, 3.0, 3.6, 4.2, 4.8, 5.4 and 6.0 m lengths | Made to length, 1.8 to 12 m | 6.5 and 12 m lengths | 2.4, 3.6, 4.8 and 6.0 m lengths |
| Lowest finished deck height | 253 mm90 × 45 joists on 2 / 140 × 45 bearers under a 23 mm board, with no air gap. | 223 mmB100-12 joists on B100-12 bearers under a 23 mm board, with no air gap. | 248 mmRHS 75 × 50 × 1.6 joists on RHS 150 × 50 × 2.0 bearers under a 23 mm board, with no air gap. | 79 mmThe designer frames it from 79 mm with joists on bearers. Clickdeck’s own lowest finished height is 51 mm, with its 28 profile used as a joist on its own, under a 25 mm board. (Clickdeck Design Guide) |
| Where it wins | A backyard deck with air under it. Easy to cut, notch and change on the day. | Low decks over damp ground, termite country and bushfire sites: Spantec says it won’t warp or rot, with no termite issues. (Spantec deck page) | A galvanised RHS frame, screwed together on adjustable piers, from standard stock lengths. (InfraBuild DuraGal RHS and SHS range) | The lowest decks, slabs, balconies and roofs, on its own Pedestal Pro pedestals. (Clickdeck pedestal guide) |
| What to watch | WoodSolutions: under 400 mm of clearance, step up to H4 or a Class 1 hardwood. Timber Queensland: H3 for bearers and joists more than 150 mm above the ground, H5 for posts in the ground. (WoodSolutions use classes; Timber Queensland TDS 4) | Any cut made on site leaves an edge without the factory coating: ask the supplier how to treat it. Keep it apart from aluminium in the wet. | InfraBuild asks for a structural sign-off for each site, says it isn’t for marine exposure or beside pool splash zones, and its guides cover timber decking only: composite boards and hidden clips on DuraGal aren’t covered. (InfraBuild DuraGal Technical Information Guide) | Clickdeck asks for a structural assessment of decks over 600 mm high. (Clickdeck Design Guide) |
| Fixings | Timber Queensland: hot-dip galvanised or stainless bolts and screws, not zinc-plated, and standard galvanised joist hangers only under a roof. Tape the joist tops. (Timber Queensland TDS 4; Trex installation steps) | Self-drilling screws, with the board pre-drilled a little larger than the thread (ModWood). Steel joists are pre-drilled for clip screws (Ekodeck). (ModWood fixing to steel; Ekodeck product manual) | Self-drilling screws: four No.10-16 × 16 per Unitie bracket where a joist crosses a bearer. (InfraBuild DuraGal Assembly Guide) | Clickdeck’s hold-down clips and hex screws, and board clips or screws made for a metal frame. Keep galvanised steel off it in the wet. (Clickdeck Design Guide; Ekodeck product manual) |
| Maker’s documents |
Every size, length and support is the catalogue the designer frames with. Each name links to its span tables. The lowest height is the shallowest joist on the shallowest bearer, with no air gap: leave more for air under a timber frame.
Steel deck framing
Spantec Boxspan and InfraBuild DuraGal
A steel deck frame is galvanised steel joists and bearers on steel posts or pedestals, under the same composite boards as a timber frame. It won’t rot, termites can’t eat it, and it stays straight. (Spantec deck page)
Spantec Boxspan is a roll-formed beam of G550 steel with a Z450 coating, made to length from 1.8 to 12 m, in 8 sizes from B100-12 to B250-20. It stands on Ezipier steel posts or Buzon pedestals. (Spantec Boxspan product page; Spantec Boxspan Residential Design Guide; Spantec Ezipier page)
InfraBuild DuraGal is RHS joists and bearers of C450L0 steel with a ZB 135/135 coating, screwed together on adjustable SHS piers, in 6.5 and 12 m lengths. InfraBuild’s guides cover timber decking only: composite boards and hidden clips on DuraGal aren’t covered, and it isn’t for marine exposure or beside pool splash zones. (InfraBuild DuraGal RHS and SHS range; InfraBuild DuraGal Technical Information Guide)
Where steel wins
- Low decks over damp ground. Pine with less than 400 mm of clearance steps up to H4 or a Class 1 hardwood (WoodSolutions use classes). Steel doesn’t care whether it dries.
- Termite country. Spantec lists “no termite issues”, and Timber Queensland asks for termite protection that can be inspected. (Spantec deck page; Timber Queensland TDS 4)
- Bushfire zones. At BAL-40 or in the flame zone, an open deck’s supports and framing must be bushfire-resisting timber or “suitable alternatives to timber”, and treated pine isn’t on the list. Spantec sells its steel as non-combustible. (WoodSolutions bushfire guide; Spantec deck page)
- Straight joists. Composite boards follow the joists, and Spantec says its steel won’t warp. (Spantec deck page)
What steel asks of the builder
- Self-drilling screws. ModWood asks for them on steel, with the board pre-drilled a little larger than the screw thread. Ekodeck says steel joists must be pre-drilled for clip screws. (ModWood fixing to steel; Ekodeck product manual)
- Cut edges. A cut made on site leaves an edge without the factory coating. Ask the supplier how to treat it.
- Keep it away from aluminium in the wet. See “Can galvanised steel touch aluminium?” below.
- Steel stumps in the ground. The building code asks for steel stumps to be fully enclosed and sealed with a welded top plate, and encased in concrete finishing at least 100 mm above the ground. (NCC Housing Provisions 4.2.13) The footings and posts calculator sizes the pads.
Aluminium deck framing
Clickdeck
An aluminium deck frame is light aluminium joists and bearers on posts or adjustable pedestals. It builds the lowest decks: Clickdeck puts its lowest finished height at 51 mm. (Clickdeck Design Guide)
Clickdeck comes in 28, 55, 110, 150 and 200 profiles, with 55 and 100 × 100 posts and its own Pedestal Pro pedestals from 10 to 440 mm, in 2.4, 3.6, 4.8 and 6.0 m lengths. The designer frames it from 79 mm with joists on bearers. (Clickdeck Design Guide; Clickdeck pedestal guide)
Where aluminium makes sense
- Low decks and doorsteps, where pine and steel can’t fit under the boards.
- Slabs, balconies and rooftops. Pedestals stand on the surface, so nothing is fixed through a membrane. Check the added weight and the waterproofing with whoever looks after the roof first. (Clickdeck pedestal guide)
- Bushfire sites. At BAL-40 or in the flame zone, the framing must be bushfire-resisting timber or a “suitable alternative to timber”. (WoodSolutions bushfire guide) Whether aluminium is accepted on your block is your certifier’s call.
What it costs and asks
- It costs more. On a 4.8 × 3.6 m deck 600 mm high, the aluminium frame is typically $7,400–$8,000 against $2,200–$3,000 in treated pine.
- Clips and screws made for metal. Board makers list different screws for metal joists than for timber. (Ekodeck product manual)
- A structural check over 600 mm. Clickdeck asks for decks higher than that to be assessed. (Clickdeck Design Guide)
- No galvanised steel touching it in the wet. Use the maker’s own brackets and screws.
Treated pine deck framing
MGP10, H3 and H4
A treated pine deck frame is MGP10 pine joists and bearers, H3 where it can dry out and H4 close to the ground. It’s the cheapest of the three frames on the example deck, and the easiest to change on site.
The designer frames pine with 90 × 45, 140 × 45, 190 × 45 joists and 2 / 140 × 45, 2 / 190 × 45 bearers on 90 × 90 H4 posts or pedestals, in 2.4, 3.0, 3.6, 4.2, 4.8, 5.4 and 6.0 m lengths. (Hyne T3 Green)
H3 or H4: the rule
- H3 more than 150 mm above the ground, H5 for posts set in it. That’s Timber Queensland’s deck data sheet for bearers, joists and posts. (Timber Queensland TDS 4)
- H4 or a Class 1 hardwood under 400 mm of clearance. WoodSolutions draws that line for framing close to the ground, and the designer applies it: any member at or under 400 mm from the ground is specified H4. (WoodSolutions use classes)
Fixings and joist tape
- Hot-dip galvanised or stainless bolts and screws, not zinc-plated. Standard galvanised connectors, such as joist hangers, only under a roof. Where the pine stays damp, stainless or epoxy-coated connectors. (Timber Queensland TDS 4)
- Tape the joist tops, where every fixing goes in. One board maker suggests its self-adhesive tape over the joists, and WoodSolutions recommends flashing strips or damp-proof membranes over exposed beams and joists. (Trex installation steps; WoodSolutions use classes)
What a deck frame costs
Typical prices, materials only
For a 4.8 × 3.6 m deck 600 mm high on posts, the frame typically costs $2,200–$3,000 in treated pine, $4,600–$6,000 in Spantec Boxspan steel and $7,400–$8,000 in Clickdeck aluminium. Materials only, inc GST.
| Frame | 600 mm high, on posts | 600 mm high, on a slab (pedestals) | 1,000 mm high, on posts |
|---|---|---|---|
| Treated pine MGP10 | $2,200–$3,000 | $1,300–$1,800 | $2,100–$2,900 |
| Spantec Boxspan steel | $4,600–$6,000 | $3,200–$4,300 | $4,600–$6,000 |
| Clickdeck aluminium | $7,400–$8,000 | $6,200–$6,700 | $7,600–$8,300 |
What changes the number
- Pedestals. On a slab, pedestals replace the posts, stirrups and footing concrete: the same pine frame drops to $1,300–$1,800.
- Height. Higher decks need longer posts and more height on the pedestals. Pine can cost less higher up: at 600 mm its bearers sit within 400 mm of the ground and go H4, at 1,000 mm they stay H3 ($2,100–$2,900).
- Joist centres. The board sets them, and closer centres mean more joists. Every frame here is worked at 400 mm or closer.
- The deck’s depth. A deep joist can span the whole depth on two bearers, or a shallower one can sit on three. The designer weighs the supports, the bearer lines and the frame’s depth when it picks the layout.
Typical Australian retail prices we have recorded from 79 sellers (checked 16 Nov 2026), inc GST. Materials for the frame only: joists, bearers, posts or pedestals, footing concrete at the designer’s planning pad sizes, brackets and frame fixings. No labour, no boards, and the board’s own clips and screws left out. Ranges are rounded out to the nearest $100. A quote from a yard will differ.
Deck framing tools and guides
- Free toolDeck designerDraw the deck in the free designer for its framing plan, materials list and cut list.
- TablesDeck span tablesJoist and bearer spans for every frame on this page.
- CalculatorDeck footings and postsPad sizes, depths, concrete and post sizes for your deck.
- CalculatorDeck joist calculatorHow many joists, how long, for any deck size.
- GuideSteel vs timber framesWhen a steel frame is worth it, and what it asks of the builder.
- GuideAluminium deck framingLow decks, rooftops and pedestals.
- GuideH3 or H4 treated pineWhich parts of a pine frame need H4.
- GuideHow to build a deck frameSet-out, footings, bearers, joists, in order.
- GuideJoist spacing for compositeWhy the board sets the centres.
- GuideGround-level composite decksFraming a deck with little room under it.
- GuideFire ratings and BALWhat a certifier asks about the boards and the frame.
- GuideHidden clips vs screwsWhich clips a maker allows on which frame.
- GuideDeck permits by stateWhen a deck needs approval, state by state.
Where these facts come from
Every size, length and lowest height is the catalogue the designer frames with. Counts, clearances and costs are the designer’s engine on the deck above. The rules and makers’ terms come from the documents below.
Frame makers
- Boxspan Steel BeamsSpantec Systems Pty Ltd · read
- Boxspan Residential Design GuideFebruary 2026 edition · Spantec Systems Pty Ltd · read
- Ezipier adjustable steel piersSpantec Systems Pty Ltd · read
- Decks (Spantec’s deck framing page)Spantec Systems · read
- DuraGal Flooring System Technical Information Guide2022 · InfraBuild Steel Centre · read
- DuraGal Flooring System Assembly GuideInfraBuild Steel Centre · read
- DuraGal Galvanized Steel RHS and SHSInfraBuild Steel Centre · read
- Clickdeck Design Guide 2026Exolux Pty Ltd (Clickdeck) · read
- Clickdeck Pedestal Installation & Specification Guide (Pedestal Pro)August 2026 · Exolux Pty Ltd (Clickdeck) · read
- T3 Green H3 treated pineHyne Timber · read
Timber industry
- Preservative Treatments and Use ClassesWoodSolutions · read
- Timber Framed Housing Options in Bushfire-prone AreasWoodSolutions · read
- Technical Data Sheet 4: Residential Timber DecksMarch 2014 (archived copy) · Timber Queensland · read
Board makers’ fixing guides
- Fixing Decking to Steel2018 · ModWood Technologies · read
- Ekodeck Classic Product ManualV9.26 · Ekodeck · read
- Decking installation stepsTrex Australia · read
Building code
- NCC 2022 Housing Provisions, Part 4.2 Footings, slabs and associated elements (4.2.13 steel stumps)NCC 2022 · Australian Building Codes Board · read
- NCC 2025 Housing Provisions, Part 6.2 Subfloor ventilation (Table 6.2.1b ground clearance)NCC 2025 · Australian Building Codes Board · read
Span figures live on the deck span tables page, each at or under the frame maker’s own published figure.
Deck framing questions
Is a steel deck frame worth it over timber?
Where timber would be the first thing to fail, yes. On a 4.8 × 3.6 m deck 600 mm high, a Boxspan steel frame typically costs $4,600–$6,000 against $2,200–$3,000 for treated pine. Steel earns that on a low deck over damp ground, in termite country, or on a BAL-40 or flame-zone block, where treated pine isn’t a bushfire-resisting timber. (WoodSolutions bushfire guide) On a high, dry backyard deck, pine does the job.
How low can a deck frame go?
51 mm finished height for Clickdeck aluminium, by Clickdeck’s own figure (Clickdeck Design Guide), and 79 mm as the designer frames it, with joists on bearers. With a 23 mm board, Boxspan steel needs at least 223 mm and treated pine 253 mm. To stay H3, pine wants to be more than 150 mm above the ground, with 400 mm or more of clearance under it (Timber Queensland TDS 4; WoodSolutions use classes).
Can you use aluminium joists under composite decking?
Yes. Clickdeck’s frame comes in 28, 55, 110, 150 and 200 profiles, on posts or its own Pedestal Pro pedestals. (Clickdeck Design Guide) Fix the boards with clips or screws made for a metal frame, and set the joists at the board maker’s centres. (Ekodeck product manual)
Do steel joists need special screws?
Yes: self-drilling screws. ModWood’s sheet for steel frames asks for them, with a pre-drilled hole in the board slightly larger than the screw thread, and Ekodeck says steel joists must be pre-drilled for clip screws, the drill size set by the steel’s thickness. (ModWood fixing to steel; Ekodeck product manual)
What joist spacing does a steel or aluminium frame need?
The same as timber: the board sets it, not the frame. Of the 73 board ranges we list, 36 allow 450 mm on a home deck and 32 need 400 mm or closer. One maker sets 400 mm for timber and metal frames alike. (Trex installation steps) The span tables page charts every range.
Which deck frame is cheapest?
Treated pine, at typical prices. On a 4.8 × 3.6 m deck 600 mm high it’s about $2,200–$3,000 for the frame, against $4,600–$6,000 for Boxspan steel and $7,400–$8,000 for Clickdeck aluminium. On a slab, with pedestals instead of posts, the pine frame is about $1,300–$1,800. A quote from a yard will differ.
Can galvanised steel touch aluminium?
Not directly. Clickdeck’s design guide asks for hot-dip galvanised steel with a non-conductive packer wherever its aluminium meets steel, a plastic or EPDM packer with at least 2 mm of clearance under bolted aluminium, at least 5 mm of clearance from natural ground, and no aluminium cast into rapid-set or lime-containing concrete. (Clickdeck Design Guide) Use the frame maker’s own brackets and screws, and put that packer between the two where an aluminium frame meets a galvanised post or ledger.
These are concept figures to help you plan and price a deck frame. They aren’t a plan sign-off.